Project Schedule
January/February
2005
Preparation
-
Public survey 1 developed
-
Funding bodies notified of project
-
Press notified of project
-
Libraries compile and submit
statistical and stakeholder information
March 2005
Step One - Lay the Foundation
April/May 2005
Step Two - Internal Operations
-
Step One Report due April 4 -
Available Now!
-
Libraries compile statistics and
information on operations
-
Public Survey 1 results compiled
and analyzed
-
KC Consesus and Tom Hennen conduct
in person interviews with staff
-
Step Two Report (Potential
Improvements to Operations) due May 30 - Available
Now!
June/July 2005
Step Three - Collaboration
-
KC Consensus continues research
into collaboration options
-
KC Consensus conducts phone
interviews with staff on options
-
Draft document on possible
collaborations due June 24
-
KC Consensus conducts site visits
-
Public Survey 2 developed
-
Step Three (Areas for
Collaboration) due July 29
August 2005
Step Four - Consolidation of Steps
One through Three
September/October
2005
Step Five - Public Judgment
-
Discussion Guides completed and
mailed to directors September 1
-
KC Consensus conducts planning
sessions with directors
-
Final Discussion Guide completed
September 16
-
Public Meeting sites facilitated and
advertised
-
Public Meetings October 9 through
October 14
-
Combined Report on all forums due
October 28
-
Public Survey 2 compiled and
analyzed
November/December
2005
Step Six - Final Report
-
Final draft of report due November
16
-
Draft reviewed by libraries and KC
Consensus by November 30
-
Report revised and designed
December 9
|